Complete acoustic design package for the MediaVerse 3-room studio. MEP engineering required before construction procurement.
10-phase critical path with hold points. The master construction order.
LiveAcoustic panel placement maps for all 3 rooms. 14 panels installed (VO Live 5 + Control 3 + Video/Podcast 6) + corner bass traps + ceiling clouds + 125Hz membrane traps.
LiveEvery wall/floor/ceiling penetration sealed to maintain STC ratings.
LiveWall-to-floor, wall-to-ceiling, and wall-to-wall junction details.
LiveRT60 (Reverberation Time), NC (Noise Criteria), STC (Sound Transmission Class) verification procedures.
LiveAll hold points and QC gates across the 10 construction phases.
LiveVO Live ↔ Control Room stagebox chain plus the Video/Podcast SNK-2 stagebox → Control patchbay audio tie (S3 BOQ SN-02/SN-04); local recording stays fully supported.
LiveCRI (Color Rendering Index) ≥95 LED fixtures, DALI (Digital Addressable Lighting Interface) control, dimming.
LiveDamascus-sourced substitutes for imported acoustic materials.
LiveEgress routes, fire-rated assemblies, detection, suppression.
LiveAll 6 wall types (W1–W6) with layer-by-layer construction details.
LiveD1–D3 + D5 doors + OW-1 observation window. STC ratings, seals, hardware.
LiveFloat floor (Sylomer SR28 + T&G plywood) and acoustic ceiling systems.
LiveComplete material data sheets: Rockwool, Green Glue, gypsum, sealants.
Live6-surface interior views for all 3 rooms: 4 walls + ceiling + floor build-up. Interactive lightbox, zoomable drawings.
Live16 wall elevation drawings with acoustic treatment layout, MEP penetrations, electrical outlets, and dimension lines.
LiveSub-panel, AV circuits AV-01–AV-03, isolated ground, Cat6A routing.
LiveDuct sleeve details, fire stops, acoustic seals at every HVAC (Heating, Ventilation, and Air Conditioning) penetration.
LiveInteractive SVG floor plan with toggle layers.
LiveD3 + buffer-spine sound lock for VO Live (D2 deleted Rev2 — Control uses external D5). Clearances, sequencing, seal requirements.
LiveMonitor positioning, mic placement, camera throw, and equipment layout for all rooms.
LiveCustom L-shaped Control Room desk. Steel frame, birch plywood, SSL UF8 recess. Full build spec.
LiveAbsorption panels (14 installed / 16 ordered), bass traps (14: 6 full-height + 1 soffit + 6 superchunk + perimeter bass soffit), 125Hz membrane traps (10), QRD diffusers (2). Materials, tools, mounting.
LiveBuild acoustic doors STC 40/45/48. Leaf construction, frame specs, seal types.
LiveRoom-by-room floor, wall, and ceiling finishes. Paint, vinyl, carpet, skirting specs.
LiveDoor hardware for D1-D3 + D5. Hinges, seals, closers, drop seals, maintenance schedule.
LiveD1–D3 + D5 cross-sections, threshold details, frame rebates, seals, and hardware coordination.
LiveOne contractor-scale cross-section for each wall type W1–W6 with total thickness and layer labels.
LiveSlab-to-finish section, Sylomer pad plan, and perimeter isolation joint detail.
LiveOW-1 triple-pane cross-sections, 5° tilt, sill level, and 7-step installation sequence.
LiveConduit, cable, duct, and pipe sealing details with acoustic / fire coordination callouts.
LiveRoom-by-room pad layouts, perimeter gap lines, column keep-outs, and order quantities.
Live10 mm isolation gap details, column clearances, and wrong-vs-right skirting conditions.
LiveWall-to-floor, partition head, concrete ceiling edge, corner junction, and column isolation details.
LiveFrench cleats, anchor isolation, bass trap corner mounting, and QRD diffuser installation heights.
LiveSB-01 face plate, sealed W6 conduit penetration, local Studio floor-box services, and Control rack landing.
LiveRun A, B, B1, B2, and C silencer sections with installation spacing and IDU-03 crossover warning.
LiveAcoustic ceiling section, perimeter wall angle, plenum barriers, and Video/Podcast T-grid layout.
LiveLegacy contractor drawing package covering floor plan, sections, column isolation, door assembly, and observation window references.
Live10-phase flowchart with swim lanes, durations, trade ownership, and formal hold points before downstream work.
LiveRACI allocation for procurement, installation, consultant review, and commissioning responsibilities.
LiveDamascus-market substitution table with performance deltas, adjustments, and must-import warnings.
LiveDamping mechanism, blob pattern, cure timing, common mistakes, and wall-by-wall applicability.
LiveRT60, NC, and field D'nT,w test layouts with acceptance criteria and critical pass notes.
LivePlan, elevation, and cable-management references for the Control Room joinery package.
LivePrintable phase-by-phase checklist with hold-point summary and signature lines for inspection walks.
LiveSimplified floor-plan overlay of audio, power, data, video, and tally routes with acoustic penetration callouts.
Live| Item | Requirement | Marker |
|---|---|---|
| Float floor perimeter | 10 mm gap → backing rod → Tremco sealant | [AC] |
| Structural columns | 10 mm air gap from ALL framing — COL_W (60×50 cm) & COL_E (60×55 cm) | [AC] |
| Ceiling clear height | 275 cm in VO Live & Control; 340 cm (HIGH) in Video/Podcast | [AC] |
| HVAC duct routing | Buffer spine ONLY — no duct penetrations through acoustic walls | [AC] |
| Green screen outlet ST-GS | Exactly 265 cm AFF, east wall, Video/Podcast | [AC] |