Installation Sequence

The full build order — each step links to its IKEA-style guide
1
Float floor   open step-by-step →
2
Walls W1/W2 (RSIC)   open step-by-step →
3
Walls W3/W4/W5/W7 (Green Glue)   open step-by-step →
4
W6 + window wall   open step-by-step →
5
Ceiling + clouds + access panel   open step-by-step →
6
Doors + magnetic seal   open step-by-step →
7
Observation window OW-1   open step-by-step →
8
Acoustic treatment   open step-by-step →
9
HVAC acoustic interface   open step-by-step →
10
Electrical + LV cabling   open step-by-step →
11
Studio desk (buy + install)   open step-by-step →
12
Commissioning   open step-by-step →
Build bottom-up and decoupled-first: float floor → walls → ceiling → openings → treatment → services → desk → commissioning. Hold points: HVAC NC before sealing ceiling, and door/window seals before sign-off.