Installation Sequence
10-Phase Construction Critical Path with Hold Points
Type C — Construction Guide · All phases must be completed in order · 6 phases are acoustically critical
Overview
This document defines the construction sequence for the MediaVerse Studio Complex. The 10 phases must be executed in strict order — each phase has prerequisites that depend on the previous phase being complete and signed off. Six of the ten phases are acoustically critical [AC] and require hold-point inspections [HP] before proceeding.
| Phase | Name | AC Critical | Hold Points |
| 01 | Site Preparation & Set-Out (empty shell — NO demolition) | — | 0 |
| 02 | MEP First Fix | — | 1 |
| 03 | Float Floor Construction | [AC] | 2 |
| 04 | Wall Framing & Decoupling | [AC] | 2 |
| 05 | Cavity Insulation & Green Glue | [AC] | 1 |
| 06 | HVAC Rough-In & Above-Ceiling | [AC] | 2 |
| 07 | Plenum Barriers & Ceiling Systems | [AC] | 1 |
| 08 | Doors, Windows & Seals | [AC] | 2 |
| 09 | Electrical Finishing & Data | — | 1 |
| 10 | Acoustic Treatment & Commissioning | [AC] | 2 |
Phase 1: Site Preparation & Set-Out
Phase 01 of 10
Site Preparation & Set-Out (empty shell — NOTHING TO DEMOLISH)
Prerequisites: Approved construction drawings (B301–B308), site access, safety plan. The B3 zone is ONE EMPTY OPEN SHELL (S3-SITE-TRUTH §1) — no interior partitions exist on site; the buffer spine and the VO/Control partition are NEW BUILDS. No demolition permit, no demolition scope.
Steps
- Survey existing basement space — confirm slab-to-slab height is 366.4 cm
- Mark zone boundaries on slab: south wall 737 cm, north wall 860 cm, east wall 431 cm, NW diagonal 448 cm
- Locate and mark columns: COL_W at (369.1, 140.6) and COL_E at (762.1, 138.1)
- Protect + isolate structural columns COL-W and COL-E (BOQ SP-01) — never remove
- Survey + protect the EXISTING high-level MEP corridor along the west/north edge — insulated duct, spiral ducts, cable trays, live cabling, smoke detection (BOQ SP-02, S3-SITE-TRUTH §4); coordinate with plenum/silencer routing BEFORE any ceiling work; keep live services live
- Clear loose site materials/debris (BOQ SP-03) — clean slab surface, level any high spots exceeding 5mm
- Verify structural slab can support float floor dead load (approx 45 kg/m²)
QC Checklist
- Slab-to-slab height confirmed at 366.4 cm (±5mm)
- Zone perimeter dimensions match SSOT within ±25mm
- Column positions confirmed within ±15mm of SSOT coordinates
- Slab surface clean and level
Do NOT: Begin any framing or floor work before set-out is verified against the drawings (laser) and the slab is verified clean and level. There is NO demolition scope on this project.
Phase 2: MEP First Fix
Phase 02 of 10
MEP First Fix (Conduit, Duct Sleeves)
Prerequisites: Phase 1 complete. Approved MEP drawings. Conduit and sleeve materials on site.
Steps
- Install sub-panel location: 240V/50Hz, 32A main breaker, TN-S earthing, star topology
- Route conduit runs for 5 circuits: AV-01 (Control, 16A/480W IG), AV-02 (VO Live, 16A/385W IG), AV-03 (Video/Podcast AV only, 16A/660W IG) + LX-1/LX-2 (production lighting, 2×16A RCBO — lighting NEVER shares AV-03)
- Install duct sleeves through future wall positions — oversized by 25mm all around for acoustic isolation
- Route Cat6A S/FTP data conduit (25mm EMT) — maintain 300 mm separation from power runs
- Install green screen power outlet conduit at 265 cm AFF on Video/Podcast east wall [AC]
Hold Point HP-2.1: Verify all conduit penetrations are oversized for acoustic sealing. Do not proceed to Phase 3 until MEP first fix is inspected. [HP]
QC Checklist
- All conduit runs installed per drawing
- Duct sleeves oversized by 25mm minimum
- Power/data separation ≥300 mm maintained
- Green screen outlet at exactly 265 cm AFF
- Floor box positions match SSOT workstation coordinates
Do NOT: Pour float floor before MEP first fix is complete. Any under-slab conduit must be in place now.
Phase 3: Float Floor Construction [AC]
Phase 03 of 10 — Acoustically Critical
Float Floor Construction
Prerequisites: Phase 2 complete and signed off. Sylomer SR28 pads, 2×18mm T&G plywood, and backing rod + Tremco sealant on site.
Steps
- Lay Sylomer SR28 isolation pads on clean slab — grid pattern per manufacturer spec, minimum 25% coverage
- Install first layer of 18 mm T&G plywood over Sylomer pads — stagger joints
- Install second layer of 18 mm T&G plywood perpendicular to first layer — glue and screw
- Maintain 10 mm perimeter gap around ALL edges [AC]
- Do NOT allow float floor to touch any wall, column, or fixed structure
- Install backing rod into 10 mm perimeter gap
- Apply Tremco acoustic sealant over backing rod [AC]
Hold Point HP-3.1: Verify 10 mm perimeter gap exists continuously around entire floor perimeter before sealant application. Gap must not be bridged at any point. [HP]
Hold Point HP-3.2: Verify float floor total buildup is 15 cm (±2mm). Resulting ceiling AFF must be 275 cm. [HP]
Column Isolation
At COL_W (60×50 cm) and COL_E (60×55 cm): float floor must maintain 10 mm air gap from column faces on all sides. Use backing rod + Tremco to seal gap. [AC]
QC Checklist
- Sylomer pads correctly placed, no gaps in grid
- Two layers of 18 mm plywood installed, joints staggered
- 10 mm perimeter gap continuous — no bridging anywhere
- Column air gaps maintained at both COL_W and COL_E
- Backing rod + Tremco sealant applied to all gaps
- Floor level within ±2 mm across zone
- Total buildup = 15 cm, ceiling AFF = 275 cm
Do NOT: Allow any rigid connection between float floor and structure. Do NOT bridge the perimeter gap with screws, adhesive, or debris. Do NOT start wall framing until floor is complete and level.
Phase 4: Wall Framing & Decoupling [AC]
Phase 04 of 10 — Acoustically Critical
Wall Framing & Decoupling
Prerequisites: Phase 3 complete (float floor level and sealed). All wall materials on site. RSIC-1 and RSIC-V clips available.
Wall Schedule
| Wall | Type | Lab STC | Field STC | Assembly |
| W1 | North concrete | 65 | 58–62 | 300mm concrete + 25mm air + RSIC-1 + hat channel + 50mm RW + 2×gyp |
| W2 | NW diagonal | 65 | 58–62 | 300mm concrete + RSIC-V clips |
| W3 | East server wall | 62 | 55–59 | Decoupled stud lining: existing concrete + 100mm air gap (to server room) + 70mm steel studs with RW70 + 2×16mm gyp+GG each face (per SSOT W3 assembly) |
| W4 | South rebuilt | 50 | 44–48 | 2×12.5mm gyp + Green Glue + 100mm studs+RW + 2×12.5mm gyp + Green Glue |
| W5 | Buffer spine | 55 | 49–53 | 2×12.5mm gyp+GG + 100mm studs+RW + 2×12.5mm gyp+GG |
| W6 | VO/Control partition | 53 | 47–51 | 2×12.5mm gyp + 70mm studs+RW + 2×12.5mm gyp + obs. window OW-1 |
Steps
- Install floor tracks on float floor — use acoustic isolation strip under all tracks
- Frame buffer spine (W5) first: west face at X=213.6 cm, east face at X=228.6 cm [AC]
- Frame perimeter walls W1–W4 with RSIC clips where specified
- Frame interior partition W6 (VO/Control)
- At COL_W: maintain 10 mm air gap between all framing and column faces [AC]
- Verify Control Room south wall width = 213.6 cm [AC]
- Verify Video/Podcast width = 479 cm [AC]
Hold Point HP-4.1: Verify buffer spine position: west face X=213.6 cm, east face X=228.6 cm (±5mm). [HP]
Hold Point HP-4.2: Verify COL_W air gap is 10 mm on all faces — no framing touching column. [HP]
QC Checklist
- All wall positions match SSOT dimensions
- Buffer spine at correct X coordinates
- RSIC clips installed per manufacturer spec on W1, W2
- Isolation strip under all floor tracks
- COL_W 10 mm air gap confirmed
- Control south = 213.6 cm, Video/Podcast width = 479 cm
- All studs plumb and level
Do NOT: Allow any stud to directly contact concrete structure without RSIC or isolation. Do NOT bridge the column air gap. Do NOT proceed to insulation until framing is inspected.
Phase 5: Cavity Insulation & Green Glue [AC]
Phase 05 of 10 — Acoustically Critical
Cavity Insulation & Green Glue Application
Prerequisites: Phase 4 complete (all framing inspected). Rockwool, Green Glue, and gypsum on site.
Steps
- Install Rockwool insulation in all wall cavities — friction fit, no gaps, no compression
- W1: 50 mm Rockwool in RSIC cavity
- W3: decoupled stud lining — 70mm steel studs with RW70; 100mm air gap to server room (per SSOT W3 assembly)
- W4: 100 mm Rockwool between studs
- W5 (buffer spine): 100 mm Rockwool between studs
- Apply Green Glue between gypsum layers on W3, W4, and W5 — 2 tubes per 1200×2400 sheet [AC]
- Install first layer of gypsum on all walls
- Apply Green Glue to first layer, install second layer
- Tape and finish all joints
Hold Point HP-5.1: Verify all cavities are fully insulated with no gaps, voids, or compressed batts before closing with gypsum. [HP]
Green Glue Application Guide
| Wall | Layers with GG | Coverage | Tubes per Sheet |
| W3 | Both sides (2×16mm gyp+GG) | Full | 2 |
| W4 | Both sides (2×12.5mm gyp+GG) | Full | 2 |
| W5 | Both sides (2×12.5mm gyp+GG) | Full | 2 |
QC Checklist
- All cavities fully insulated — no gaps visible
- Green Glue applied at correct coverage (2 tubes/sheet)
- Gypsum layers installed with staggered joints
- All joints taped and finished
Do NOT: Compress insulation batts to fit. Do NOT leave any cavity partially filled. Do NOT skip Green Glue on specified walls — it provides 3–6 dB additional STC.
Phase 6: HVAC Rough-In & Above-Ceiling [AC]
Phase 06 of 10 — Acoustically Critical
HVAC Rough-In & Above-Ceiling Pulls
Prerequisites: Phase 5 complete (walls closed). IDU units, silencers, ductwork, and flex connectors on site.
IDU Installation
| Unit | Capacity | Location | Serves |
| IDU-04 | 1.0 TR | North wall, VO Live side | VO Live only (dedicated) |
| IDU-03 | 1.0 TR | North wall, Control zone | Control Room (dedicated) |
| IDU-05 | 1.0 TR | North wall, Video/Podcast side | Video/Podcast only (dedicated) |
System: Daikin VRF (NOT Samsung). ODU: 1× outdoor unit, south side.
Silencer Schedule — 4 Runs
| Run | Length | Attenuation | Max Velocity | NC Max | Serves |
| A | 1500 mm | 40 dB | 1.5 m/s | NC-12 | VO Live (dedicated) |
| B | 1000 mm | 25 dB | 2.5 m/s | — | Trunk to Control branch (B1) |
| B1 | 500 mm | 15 dB | 2.0 m/s | NC-18 | Control branch |
| C | 1000 mm | 25 dB | 2.0 m/s | NC-18 | Video/Podcast (dedicated) |
Steps
- Mount IDU-04, IDU-03, IDU-05 on north wall at specified positions
- Install silencer Run A (1500 mm) in VO Live ceiling plenum [AC]
- Install Run B (1000 mm) routing through buffer spine to Control branch [AC]
- Install branch silencer B1 (500 mm) to Control Room
- Install silencer Run C (1000 mm) in Video/Podcast ceiling plenum
- Use flex connectors at all IDU-to-duct and duct-to-silencer connections [AC]
- Install 6 fresh air terminals (2 per room) in ceiling plenum
- Seal all duct penetrations through walls with acoustic sealant
Hold Point HP-6.1: Verify all 4 silencer runs are installed at correct lengths and positions before closing ceiling. [HP]
Hold Point HP-6.2: Verify all duct penetrations through buffer spine are acoustically sealed. [HP]
QC Checklist
- 3 IDUs mounted at correct positions
- All 5 silencer runs (A, B, B1, B2, C) installed (A, B, B1, C) — lengths verified
- Flex connectors at all mechanical joints
- 6 fresh air terminals installed (2 per room)
- All duct penetrations sealed
- No rigid duct-to-structure connections
Do NOT: Use rigid connections between ductwork and structure. Do NOT route ducts through walls without acoustic sealing. Do NOT combine or omit any of the 4 silencer runs.
Phase 7: Plenum Barriers & Ceiling Systems [AC]
Phase 07 of 10 — Acoustically Critical
Plenum Barriers & Ceiling Systems
Prerequisites: Phase 6 complete (all HVAC installed and sealed). Ceiling grid, tiles, and plenum barrier materials on site.
Ceiling Schedule
| Room | System | NRC | Coverage | Height AFF |
| VO Live | Rockfon Sonar E (cloud) | 0.90 | 28% | 275 cm |
| Control Room | Rockfon Sonar E (cloud) | 0.90 | 28% | 275 cm |
| Video/Podcast | Rockfon Sonar E (cloud) | 0.90 | 28% | 340 cm (HIGH) |
Steps
- Install plenum barriers above all inter-room walls to prevent sound flanking through ceiling void
- Extend wall framing to underside of structural slab where plenum barriers are required
- Install ceiling grid at 275 cm AFF in VO Live + Control; Video/Podcast ceiling grid at 340 cm AFF (HIGH) [AC]
- Install ceiling tiles per room schedule above
- Verify audio-room ceiling plenum depth = 76 cm (slab-to-slab 366.4 − ceiling 275 − floor 15 ≈ 76 cm)
Hold Point HP-7.1: Verify plenum barriers are continuous and sealed above all inter-room walls. No gaps allowed. [HP]
QC Checklist
- Ceiling height = 275 cm AFF (VO Live + Control); 340 cm AFF (Video/Podcast, HIGH)
- Plenum barriers continuous above all partitions
- Correct ceiling tile type installed per room
- Ceiling grid level and square
- Audio-room plenum depth = 76 cm
Do NOT: Leave gaps in plenum barriers. Do NOT install ceiling before HVAC is complete. Do NOT drop the Video/Podcast ceiling below its 340 cm HIGH design height.
Phase 8: Doors, Windows & Seals [AC]
Phase 08 of 10 — Acoustically Critical
Doors, Windows & Seals
Prerequisites: Phase 7 complete (ceilings installed). Acoustic doors, observation window, and sealing materials on site.
Door Schedule
| Door | Size | STC | Location | Swing |
| D1 | 90×220 cm | 50 | x=479 cm (centre) south wall | Opens OUT (south) — landing + security hinges |
| D5 | 90×220 cm | 50 | Control south wall (external) | Outward (south) — D2 deleted (Rev2), Control uses external D5 |
| D3 | 80×220 cm | 45 | VO/Control partition | North into VO Live |
Observation Window
| Window | Size | STC | Location | Detail |
| OW-1 | 80×50 cm | 50 | VO/Control partition (Wall W6) | Sill 110 cm AFF, 5° tilt, triple-pane |
Steps
- Install door frames with acoustic seals on all 4 edges (head, jambs, threshold)
- Hang acoustic doors — verify STC rating labels match schedule
- Install automatic door bottoms (drop seals) on all 3 doors [AC]
- Install observation window OW-1 with 5° tilt, triple-pane glazing [AC]
- Seal all door frame and window frame perimeters with acoustic sealant
- Test all doors for proper closure and seal compression
Hold Point HP-8.1: Verify all door seals compress fully when closed — no daylight visible around any door edge. [HP]
Hold Point HP-8.2: Verify observation window OW-1 is sealed, tilted at 5°, and STC-50 rated. [HP]
QC Checklist
- All 3 doors installed with correct STC ratings
- Door seals compress on all 4 edges
- Drop seals function correctly
- Window OW-1 installed with 5° tilt
- All perimeter joints sealed
- No daylight visible around any door or window
Do NOT: Install standard (non-acoustic) doors. Do NOT skip the drop seal on any door. Do NOT install window OW-1 without the 5° tilt — parallel panes cause resonance.
Phase 9: Electrical Finishing & Data
Phase 09 of 10
Electrical Finishing & Data
Prerequisites: Phase 8 complete (doors and windows installed). Outlets, switches, patch panels, and data cable on site.
Circuit Schedule
| Circuit | Room | Breaker | Load | Utilization |
| AV-01 | Control Room | 16A | 480W | 13% |
| AV-02 | VO Live | 16A | 385W | 10% |
| AV-03 | Video/Podcast (AV only) | 16A | 660W | 18% |
| LX-1 | Video/Podcast (ceiling-grid production lighting) | 16A RCBO — Schneider Acti9 | 1600W | 43% |
| LX-2 | Video/Podcast (floor/mobile/accent lighting) | 16A RCBO — Schneider Acti9 | 900W | 24% |
Total zone load: 4025W / 52% utilization across 5 circuits. Sub-panel: 240V/50Hz, 32A main, TN-S earthing, star topology, IG conductors. Production lighting is NEVER on AV-03 — LX-1/LX-2 only.
Steps
- Install all outlets at 45 cm AFF (standard height)
- Install green screen outlet ST-GS at 265 cm AFF on Video/Podcast east wall [AC]
- Install Cat6A S/FTP data cabling — TIA-568B termination
- Maintain 300 mm separation between power and data runs
- Install patch panels and label all runs
- Seal all electrical penetrations through acoustic walls with fire-rated acoustic sealant
Hold Point HP-9.1: Verify all electrical penetrations through acoustic walls are sealed. No unsealed holes. [HP]
QC Checklist
- All outlets at correct heights (45 cm standard, 265 cm green screen)
- Power/data separation ≥300 mm
- All penetrations sealed
- Circuit loads match schedule
- Data cables tested and certified
Do NOT: Run power and data in the same conduit. Do NOT leave any wall penetration unsealed. Do NOT overload any circuit beyond its 16A rating.
Phase 10: Acoustic Treatment & Commissioning [AC]
Phase 10 of 10 — Acoustically Critical
Acoustic Treatment & Commissioning
Prerequisites: Phases 1–9 complete. All acoustic panels, bass traps, QRD diffusers, and test equipment on site.
Panel Installation Schedule
| Room | Panels | Bass Traps | QRD | Notes |
| VO Live | 5 | 3 | 0 | + manual curtain (live/dead switching) · cloud 28% |
| Control Room | 3 | 4 | 2 | 3 corner + 1 soffit trap (NE corner, above D3) · cloud 28% [AC] |
| Video/Podcast | 6 | 6 | 0 | 6 DEEP superchunk (400–600mm) · cloud 28% · multi-colour curtain backdrop (N + E-half) · deep perimeter bass soffit · in-shot rug · isolated Unistrut grid · COL_W column |
| Total installed: 16 (14 absorption + 2 QRD) | Bass traps: 12 + 1 soffit · ceiling clouds: 3 · 125Hz membrane: 10 · Order: 16 (10% waste buffer) |
Steps
- Install bass traps in VO Live (3 corners, floor-to-ceiling, 150 mm Rockwool RWA45)
- Install bass traps in Control Room (3 corners + 1 soffit trap NE corner, above D3)
- Install DEEP superchunk bass traps in Video/Podcast (6 traps, 400–600 mm: SE + SW corners + 4 at COL_W re-entrant angles, NOT NW)
- Build the deep perimeter bass soffit in Video/Podcast (MEP bulkhead, ≥300 mm mineral-wool fill + sealed cavity, α₁₂₅≈0.55) [AC]
- Install absorption panels: VO Live (5), Control (3), Video/Podcast (6) [AC]
- Install QRD diffusers: Control (2 rear wall)
- Install manual curtain in VO Live — 450g/m² velour, ceiling C-rail
- Install the Video/Podcast multi-colour curtain backdrop: motorised track on independent secondary-steel hung from the structural slab on neoprene isolation hangers (not off the resilient ceiling leaf; not rigid to the slab), 40 cm off wall, along the North wall (full) + East wall north-half; fit interchangeable ≥300 g/m², ≥100% fullness curtains (chroma green, white, black molton, mid-grey) + vinyl floor-sweep for the infinity curve [AC]
- Install the in-shot area rug (≈6 m²) in Video/Podcast to break vertical floor/ceiling flutter
- Install the isolated Unistrut lighting pipe grid in Video/Podcast on independent isolated hangers (clamp-on fixtures) — NOT fixed to the decoupled ceiling [AC]
- Install Genelec 8030C monitors in Control Room at ±30°, listening position at 1.54 m from front wall (57% of 2.70 m clear depth)
Commissioning Tests
| Test | Room | Target | Method |
| NC measurement | VO Live | NC-12 | SPL meter, octave bands, HVAC running at min fan |
| NC measurement | Control | NC-18 | SPL meter, octave bands, HVAC running |
| NC measurement | Video/Podcast | NC-18 | SPL meter, octave bands, HVAC running |
| RT60 measurement | All rooms | — | Impulse response, octave bands |
| STC field test | All walls | — | ASTM E336 (expect 3–7 dB below lab) |
Hold Point HP-10.1: NC measurements must pass before room is accepted. VO Live NC-12 requires IDU-04 at minimum fan speed. [HP]
Hold Point HP-10.2: RT60 measurements must match SSOT targets within ±10%. [HP]
QC Checklist
- All 16 treatments installed (14 absorption + 2 QRD diffusers, order 16 with 10% buffer)
- All bass traps installed floor-to-ceiling; deep perimeter bass soffit built and sealed
- Video/Podcast curtain backdrop track on independent secondary-steel hung from the structural slab on neoprene isolation hangers (NOT the ceiling leaf), 40 cm off wall; curtains and floor-sweep fitted
- Isolated Unistrut lighting grid on independent hangers — not touching the decoupled ceiling
- In-shot area rug (≈6 m²) laid in Video/Podcast
- NC targets met in all rooms
- RT60 within ±10% of SSOT targets
- STC field tests within expected range (3–7 dB below lab)
- HVAC crosstalk acceptable
- Manual curtain operational (live/dead modes)
Completion: When all hold points are signed off, the facility is ready for equipment installation and operational handover.
Do NOT: Accept NC measurements with HVAC off. Do NOT drop the Video/Podcast ceiling below its 340 cm HIGH design height. Do NOT run the curtain-backdrop track through to the structural slab — hang it from the structural slab on isolation hangers to keep the flanking path short. Do NOT hang the Unistrut lighting grid from the decoupled ceiling — use independent isolated hangers.