Construction Guide

Testing & Commissioning

NC, RT60, and STC test procedures with pass/fail criteria. All tests performed after Phase 10 with HVAC running at normal operation.

NC Testing Procedure

Equipment
Calibrated SLM, 1/1 octave band
Condition
HVAC running at normal operation
Positions
Minimum 5 per room
Standard
ANSI/ASA S12.2

Pass/Fail Criteria

RoomNC TargetPassConditional PassFail
VO Live B304NC-12≤ NC-12NC-13 to NC-15> NC-15
Control Room B311NC-18≤ NC-18NC-19 to NC-21> NC-28
Video/Podcast B312-1NC-18≤ NC-18NC-19 to NC-21> NC-28
Recovery if fail: Check IDU fan speed setting, verify silencer installation and orientation, inspect duct connections for air leaks, check flex connector lengths (≥150mm).

RT60 Testing Procedure (ASTM E2235)

Equipment
Calibrated measurement mic + impulse source
Bands
6 octave bands: 125, 250, 500, 1k, 2k, 4k Hz

VO Live B304 — Target vs Achieved

Hz1252505001k2k4k
Target0.250.220.200.180.180.18
Achieved0.280.230.200.190.180.17
Status+0.03+0.01+0.01

Control Room B311

Hz1252505001k2k4k
Target0.400.380.350.330.330.33
Achieved0.420.380.340.320.310.30
Status+0.02

Video/Podcast B312-1

Hz1252505001k2k4k
Target0.350.320.300.280.280.28
Achieved0.380.330.280.260.250.24
Status+0.03+0.01
Eyring correction: For rooms where average absorption > 0.3 (VO Live, Control), Eyring correction gives more accurate results than Sabine.
Recovery if too live: Add panels, check panel installation, inspect ceiling tile gaps.
Recovery if too dead: Remove panels, check if bass traps are overdamping.

STC Field Testing (ASTM E336)

Key partitions only — focus on the weakest links in the isolation chain. Measurement per ASTM E336 (or ISO 16283-1); single-number rating per ASTM E413 (or ISO 717-1). Acceptance = SSOT STC targets.

ElementLab STCTarget FieldTest Method
W6 — VO Live / Control partition53≥ 48 dB field D'nT,wLoudspeaker source method
D3 sound-lock door45Composite airlock — light-leak + level testSee Sound Lock Detail
Recovery if fail: Check door seals (light test), verify penetration sealing, confirm Green Glue installation (2 tubes per 4×8 sheet, applied wet).

Commissioning Report Template

FieldValue
Test date_________________
Equipment used_________________
Operator name_________________
Calibration date_________________

Per-Room Results

RoomNC MeasuredNC Pass?RT60 (500Hz)RT60 Pass?Notes
VO Live______
Control______
Video/Podcast______

Sign-off: _________________ Date: _________________