Inspection Checklist

Per-stage verification — HOLD POINTs must pass before the next trade covers the work
StageVerifyGate
Float floor25mm perimeter gap continuous; no rigid bridge to slab/wall; Sylomer not touching wallsHOLD POINT
Walls (decoupled)RSIC clips on grid, no bypass screws; leaves decoupled; STC ≥ targetHOLD POINT
Green Gluecompound BETWEEN the two boards (not on framing/edges); ~2 tubes/sheet; W3/4/5/7 only
W6 / window150mm decoupled studs; OW-1 flush; glazier STC-50 cert on fileHOLD POINT
Ceilingisolated hangers; 50mm plenum; access panel gasketed + off VO mic
Doorsmagnetic gasket continuous (paper-drag); drop seal full-width; light test passesHOLD POINT
Treatmentbass traps in corners; Editing panels installed (RT60 fails without); cleats/brackets per spec
HVACflex connectors both ends; IDU on isolators; isolated hangers; NC measured before ceiling sealHOLD POINT
Electrical/LVsingle star ground; steel conduit+boxes putty-padded; snake/XLR/Cat6/HDMI pulled before closure
CommissioningRT60 (Sabine+Eyring) + NC at design airflow + field STC measured and passedHOLD POINT
HOLD POINTs are mandatory stop-and-verify gates (esp. NC before the ceiling is sealed, and door/window seals before sign-off). See Build 12 — Commissioning.