Site Inspection Checklist
Printable inspection sheet for trade supervisors and acoustic sign-off walks. Each phase includes a dedicated signature line so the responsible inspector can record acceptance before downstream works proceed.
Format
Printable
Hold Points
HP-1 / 2 / 3 / 10
Critical Tags
[AC] + [HP]
Use
Site inspections
Hold Points Summary
Must Sign OffHP-1
Structural sign-off before floor works.
HP-2
Penetration sealing inspection before ceiling.
HP-3
Perimeter gap inspection before floor finish.
HP-10
Commissioning certificate before handover.
Phase Checklists
Inspector Signatures Per PhasePhase 1 — Pre-Construction
- ☐ Structural slab capacity confirmed ≥ 45 kg/m²
- ☐ All penetration sleeve positions marked
- ☐ MEP contractor briefed on annular gap requirement
- ☐ Green Glue delivery confirmed before wall works
- ☐ Sylomer SR28 delivery confirmed
Inspector: ____________________ Date: ____________________
Phase 2 — Wall Framing
- ☐ W3 / W4 / W5 / W6 stud positions verified
- ☐ No stud touching concrete on resilient clip walls
- ☐ RSIC-1 clips at 600 mm spacing
- ☐ Hat channel seated in clips
- ☐ No direct metal-to-metal contact through assembly
Inspector: ____________________ Date: ____________________
Phase 3 — Gypsum and Green Glue
- ☐ First layer screwed to hat channel
- ☐ GG applied to correct walls: W3, W4, W5
- ☐ GG blob pattern verified (not spread, not at edges)
- ☐ Second layer laminated within 15 minutes
- ☐ All joints staggered minimum 400 mm
Inspector: ____________________ Date: ____________________
Phase 4 — Penetration Sealing [HP]
- ☐ All conduit penetrations sealed Tremco both sides
- ☐ All duct penetrations with fire collar both sides
- ☐ Annular gaps only — no solid fill
- ☐ Sign-off by acoustic consultant
Inspector: ____________________ Date: ____________________
Phase 5 — Float Floor [HP]
- ☐ Sylomer pads at 400 mm grid
- ☐ Bottom T&G plywood installed
- ☐ Top T&G plywood staggered joints 400 mm offset
- ☐ 10 mm perimeter gap maintained all around
- ☐ Backing rod installed in gap
- ☐ Tremco sealant applied over backing rod
- ☐ Gap inspection sign-off before finish
Inspector: ____________________ Date: ____________________
Phase 6 — Ceiling
- ☐ T-grid at 275 cm AFF in VO Live + Control; Video/Podcast ceiling at 340 cm AFF (HIGH)
- ☐ 100 mm Rockwool ProRox above all tiles
- ☐ Plenum barriers at all partition intersections
- ☐ Video/Podcast MEP boxed into perimeter bulkhead (HVAC service hatch) — 340 cm clear kept over open floor
- ☐ 5 mm gap between tile and wall (no caulking)
Inspector: ____________________ Date: ____________________
Phase 7 — MEP Fit-Out
- ☐ Silencers installed per run lengths
- ☐ HVAC connections complete
- ☐ IDU-03 crossover silencer verified [HP]
- ☐ Electrical outlets at correct heights
- ☐ Data points tested for continuity
Inspector: ____________________ Date: ____________________
Phase 8 — Treatment
- ☐ All absorption panels installed per layout (VO 5 / Control 3 / Video-Podcast 6)
- ☐ 50 mm gap from ceiling and floor
- ☐ Bass traps in all room corners per spec (Video/Podcast: SE + SW + 4 at COL_W, NOT NW)
- ☐ 50 mm air gap behind bass traps
- ☐ Video/Podcast deep perimeter bass soffit built & sealed (≥300 mm mineral wool, α₁₂₅≈0.55)
- ☐ QRD diffusers at Control south (2 rear wall)
- ☐ Video/Podcast multi-colour curtain backdrop track hung from the structural slab on neoprene isolation hangers (NOT the slab), 40 cm off wall; curtains + floor-sweep fitted
- ☐ Video/Podcast isolated Unistrut lighting grid on independent hangers (NOT on the decoupled ceiling)
- ☐ Video/Podcast in-shot area rug (≈6 m²) laid
- ☐ Observation window OW-1 tilted 5° verified
Inspector: ____________________ Date: ____________________
Phase 9 — Doors
- ☐ D1 STC 50 hung and drop seal operational
- ☐ D3 STC 45 hung and drop seal operational
- ☐ D5 STC 50 hung and drop seal operational (Control external entry — D2 deleted Rev2)
- ☐ All doors: compression seal contact verified
- ☐ All doors: acoustic mortise lock operational
Inspector: ____________________ Date: ____________________
Phase 10 — Commissioning [HP]
- ☐ RT60 test completed all rooms
- ☐ NC test completed with HVAC running
- ☐ All results meet pass criteria
- ☐ Acoustic consultant certificate issued
- ☐ Client handover complete
Inspector: ____________________ Date: ____________________
Inspector: _____________ Date: _____________