Master Bill of Materials

Consolidated reference — all categories · acoustics5 · Audience: Owner, procurement, contractor

AC Acoustic Critical — cannot modify without written approval HP Hold Point — stop work, obtain sign-off

Phase Summary

Construction (BOQ Issue 1) — contractor scope
$63.1k–$94.9k (BOQ Issue 1)
Blocks $57,400–$86,300 + 10% contingency = $63,140–$94,930 — confirm by RFQ · walls, float floor, perimeter isolation, ceiling, doors, HVAC
Equipment — owner scope
~$14,962
AV gear, cameras, interfaces, studio monitors — separate from the contractor BOQ
Software — owner scope
~$9,808
DAW, plugins, subscriptions — separate from the contractor BOQ
Construction (BOQ Issue 1): $63.1k–$94.9k — blocks $57,400–$86,300 + 10% contingency = $63,140–$94,930, confirm by RFQ · Owner-supply AV equipment ≈$10.6k (separate from the contractor BOQ; indicative capex $73,722–$105,512) · Owner gear already on hand saves ~$2,783

0. Site Preparation & Protection (BOQ SP-01..SP-03)

The B3 zone is ONE EMPTY OPEN SHELL (S3-SITE-TRUTH §1) — no interior partitions exist on site; there is NOTHING TO DEMOLISH. The buffer spine (W-07) and the VO/Control partition (W-10) are NEW BUILDS.
BOQItemQtyNotes
SP-01Protect + isolate structural columns COL-W (369,140) & COL-E (762,138) — never remove1 lotPhysics lock; wrap COL-W in set
SP-02Survey + protect the EXISTING high-level MEP corridor along the west/north edge (insulated duct, spiral ducts, cable trays, live cabling, smoke detection) AC1 lotS3-SITE-TRUTH §4 (photo IMG_1291); coordinate with plenum/silencer routing BEFORE any ceiling work; keep live services live; relocations only per approved MEP shop drawing
SP-03Clear loose site materials/debris + verify set-out datums (laser) against the drawings before first fix1 lotEmpty-shell site; set-out verification precedes everything

1. Acoustic Treatment

Panel order: 16 absorption panels (10% waste buffer) · Installed: 14 absorption + 2 QRD = 16 AC
ItemSpecQty (installed)Qty (order)Notes
Absorption panelsRockwool RWA45 100mm · 1200×600mm · NRC 0.90141610% waste buffer · wool: Saudi Rock Wool Factory (KSA) / Izocam (TR) · grille cloth: Guilford FR701 AC
VO Live panelsAs above5Subset of 14 absorption
Control panelsAs above — first-reflection3Fixed position AC
Video/Podcast panelsAs above — curtain backdrop carries mid/high6Widened room (19.78 m², 3.40 m ceiling) AC
Full-height corner trapsRockwool RWA45 150mm · 300mm · floor-to-ceiling673 VO Live + 3 Control AC
Soffit trapRockwool RWA45 150mm · above door11Control — NE corner, above D3 AC
Deep perimeter bass soffitMEP bulkhead as bass device · ≥300mm mineral-wool + sealed cavity · α₁₂₅≈0.5511Video/Podcast — with HVAC service hatch AC
Superchunk deep trapsCorner superchunk · 400–600mm deep67Video/Podcast — deep LF control AC
Ceiling cloudsRockwool RWA45 100mm · fabric-wrapped33VO 28% · Control 28% · Video/Podcast 28%
125Hz membrane traps4mm ply + 100mm cavity + 50mm RWA45 · 1200×600 · f0≈123Hz10113 VO Live + 3 Control + 4 Video/Podcast — low-frequency modal control
QRD diffusersQuadratic Residue Diffuser22 + 1 spare2 Control rear · GIK Q7D (regional alt: current Vicoustic line via PULT UAE — DC2 discontinued)
Curtain backdrop systemMotorised L-track · N wall + E north-half (~23 m² face) · hung from structural slab on isolation hangers · 40cm off wall11Video/Podcast — 4 interchangeable curtains (chroma green · white · black molton · mid-grey, ≥300 g/m², ≥100% fullness) + vinyl floor-sweep; curtain fabric imported · track: Gerriets JOKER 95 + TRAC-DRIVE / ShowTex Rail H100 (ShowTex ME Dubai) · fabrics: Gerriets / ShowTex Molton CS (IFR) · floor sweep: Rosco Chroma Floor AC
In-shot area rug~6 m² · breaks vertical flutter11Video/Podcast
Isolated Unistrut lighting gridClamp-on fixtures · isolated hangers (not on decoupled ceiling)11Video/Podcast · neoprene hangers: Mason WHR / Kinetics RH

2. Doors & Windows

IDSizeSTCLocationSwingNotes
D190×220 cm50South wall x=479cm (centre)Opens OUT (S)IAC Noise-Lock (via Gulf Acoustic LLC, Dubai) AC
D380×220 cm45VO/Control partition x=163.6cm (centre)N into VO LiveAKINCO doorset Rw45 (Dubai; TR alt Dimak)
D590×220 cm50South wall x=90cm (centre) — Control externalOpens outIAC Noise-Lock (via Gulf Acoustic LLC, Dubai) AC
OW-180×50 cm50VO/Control partition · sill 110cm AFF5° tiltIAC Noise-Lock window AC

3. Wall Materials

WallSTC LabThicknessKey materials
W1 North concrete (the ONLY concrete wall — street)65300mm concrete + RSIC-1/A237R + hat channel + 50mm RWA45 + 2×12.5 SoundBloc w/ GG (BOQ PW-01)
W2 West diagonal — existing GYPSUM~60 (class)Existing gypsum wall (kept, NO fixings into it) + ≥25mm air gap + INDEPENDENT 70mm stud leaf + RWA45 + 2×12.5 SoundBloc w/ GG (BOQ PW-02) — the old "RSIC on concrete" W2 is VOID (S3-SITE-TRUTH §2)
W3 East server (existing gypsum leaf)6216 cm new build + 100mm existing air gap (kept UNFILLED) = 26cm total buildupExisting GYPSUM leaf + ~100mm existing air gap to the B313 SERVER ROOM (24/7 — the gap is the decoupler, never bridge it) + NEW decoupled 70mm stud leaf with RW70 + 2×16mm gyp+GG (BOQ PW-04)
W4 South — existing gypsum, lined/rebuilt to STC 505015 cmExisting gypsum partition lined/rebuilt (BOQ PW-03): 2×12.5mm gyp + Green Glue + 100mm studs+RW + 2×12.5mm gyp + Green Glue; D1/D5 hosted as FRAMED openings on steel subframes (BOQ D-07 — no concrete cutting, no lintels)
W5 Buffer spine — NEW BUILD5515 cmNEW BUILD (BOQ W-07 — empty shell, nothing to demolish): 2×12.5mm gyp+GG + 100mm studs+RW + 2×12.5mm gyp+GG on independent frames; head sealed to slab; only sleeved SN-03 crossings penetrate
W6 VO/Control5312 cm2×12.5mm gyp + 70mm studs+RW + 2×12.5mm gyp + OW-1 window cutout
Brands: Gypsum — Saint-Gobain Gyproc SoundBloc 12.5mm (UAE) or Knauf (KSA) · Resilient clips — Kinetics RSIC-1, regional fallback Studco Resilmount A237R (confirm ME stock at RFQ) · Putty pads — Hilti CFS-P PA · Firestop — Hilti CP 606 + CFS-C P collars · Door drop seals — Athmer Schall-Ex L-15/30 WS · Decoupled-ceiling spring hangers — Mason 30N/W30N (Kinetics Group UAE) · Neoprene hangers — Mason WHR / Kinetics RH.

4. Float Floor

ItemSpecNotes
Isolation padsSylomer SR28 — pads on a 400mm grid (not full coverage)
Plywood deck18mm T&G plywood · 2 layers · staggered joints — Turkish mill (Vemo or equal), EN 636-2 batch certs
Perimeter gap10mm → closed-cell foam backing rod → Tremco sealantAC
Column box-out COL_W60×50cm · 10mm air gapAC
Column box-out COL_E60×55cm · 10mm air gapAC

5. HVAC — System Overview

UnitRoom servedLocationNC target
IDU-04VO Live — dedicatedNorth wallNC-12 max AC
IDU-03Control Room — dedicatedNorth wallNC-18 max
IDU-05Video/Podcast — dedicatedNorth wallNC-18 max
ODUOutdoor unit (Daikin VRF)South side

6. Electrical

ItemSpec
Sub-panel240V / 50Hz · 32A · TN-S star topology
Zone load4025W (52% utilization) · 5 circuits
AV circuits (IG)AV-01 Control 480W · AV-02 VO Live 385W · AV-03 Video/Podcast 660W — 16A dedicated MCB, isolated ground, RED Schuko — Legrand Mosaic dedicated-circuit range (technical earth) + Schneider Acti9 iC60 MCB
Lighting circuitsLX-1 1,600W + LX-2 900W · 16A RCBO (LED-inrush rated) · production lighting split off AV circuit · Video/Podcast · Schneider Acti9 iC60 RCBO 16A/30mA
ConduitEMT steel: 25mm data/LV (Cat6A S/FTP), 50mm audio multicore — no PVC on audio runs
Data separation300mm min from power conduits
Standard outlets45cm AFF throughout
ST-GS outlet265cm AFF east wall Video/Podcast AC
On-air / recording signs2× illuminated on-air signs — above D1 (Video/Podcast external) + external D5 (Control external) · Sonifex LDD-40F1REC (or LD + 5–7V PSU)
Data panelsAV-01 to AV-03 · Cat6A S/FTP · TIA-568B · CommScope NETCONNECT (Ampconnect GCC)

7. AV Equipment — Phase Summary

ScopeDetailBudget
Construction (BOQ Issue 1)Contractor / acoustic build — blocks $57,400–$86,300 + 10% contingency, confirm by RFQ$63.1k–$94.9k
Owner-supply AVPer BOQ equipment analysis≈$10.6k
Equipment (owner scope)AV gear, cameras, interfaces — separate from the contractor BOQ~$14,962
Software (owner scope)DAW, plugins, subscriptions — separate from the contractor BOQ~$9,808

See AV-EQUIPMENT.html for full room-by-room schedule.